Pullman Hotel is a project in Addis Ababa, Ethiopia, where the EASE-CCL Post-Tensioning system was applied to construct the ballroom cover slab in August 2017.

The owner ENYI Real Estate and their consultant Kenmos Engineering sought our expertise to provide a solution for the 32 x 16 m ballroom.

The columns were placed solely on the periphery, and the original solution was a waffle slab of 2m depth drop beams. This would be extremely difficult to execute and costly.

We managed to arrange an easier method of execution and most importantly reduce our client’s overall cost and slab depth. This was done by utilizing only four 75 cm drop beams in one direction, and a flat slab of 24 cm in the other direction.

Knowing that they could rely on EASE-CCL for providing solutions for any challenges, our client was very content with the results.